Researching, developing and application of the interactive remote reserve power supply auto-switching device based on the optical-fiber communication
Bu mingxin1,Wu jinwen2,Wu kongsong3
(1 Hebei Handan Power Supply Company, Hebei Handan 056002,2, Handan City Depu Electric Power Automation Equipment Co., Ltd. Hebei Handan 056002,3 Shanghai acrel Electric Co., Ltd,shanghai jiading 201801)
Abstract: 110kV power grid for the online contact one end of the blackout, the original substation devices prepared from the vote since the vote can not achieve the distance function, leading to some of 110kV substation and one end of the 220kV substation site-wide blackout. Study on a use of existing fiber-optic communication channel information transmission operation, fault information and jump Reclosing command standby power mode of the program since the vote. Prepared through the transformation of the original cast from the device, increasing the number of voting logic program, the installation of fiber optic communications modules, implementation of the interface with the fiber-optic network. Handan City in Hebei Province by the 110kV grid in the application and implementation, good implementation of the tandem distance standby power grid since the vote.
Key words: 110kV power grid The distance from the vote Fiber Since the distance preparing to vote
Tao Jun,Li Wei-guo,Hong Tian-xin, Preparation of serial communications at the distance from the vote on the application of, Anhui University of electricity workers,2003,8(3),12-15
Wang Rui,Li Zhao,Xu Yuan-rong,Adaptive inter-station high-voltage power grids prepared from the cast of real-time control device,Relay,2007,35(19),45-48
[4]、唐海军,基于光纤通信的远方备自投设计与实现,继电器,2006,34 (4),80-82
Tang Hai-jun, Optical fiber communication based on the distance from the cast prepare the design and implementation,Relay,2006,34(4),80-82